Ground Bonding kit 53
4.
Place an M8 internal serrated lock washer and an M8 hex nut over the grounding lug on the cable
access panel and tighten.
From the system chassis rail to the rack top:
1.
Insert a T-25 Torx screw through one end of a 15.24-cm (6-in) grounding strap, and secure it to the
system chassis rail.
2.
Place the other end of the same grounding strap over the grounding lug on the rack top.
3.
Place an M8 internal serrated lock washer and an M8 hex nut over the grounding lug on the rack top
and tighten.
From the grounding lug on the rack top to the grounding lug on the perforated panel:
1.
Place one end of a 36.83-cm (14.5-in) grounding strap over the grounding lug on the rack top.
2.
Place an M8 internal serrated lock washer and an M8 hex nut over the grounding lug on the rack top
and tighten.
3.
Place the other end of the same grounding strap over the grounding lug on the perforated panel.
Summary of Contents for HP 10000 G2 Series
Page 35: ...Cable Management Bracket kit 35 Installation is complete ...
Page 74: ...Hook and Loop Cabling Strap Clip kit 74 ...
Page 75: ...Hook and Loop Cabling Strap Clip kit 75 Installation is complete ...
Page 104: ...Rack Air Duct kit 104 For more information see Baying kit on page 25 ...
Page 125: ...Vertical PDU Mounting kit 125 HP monitored PDU 2 Install the PDU The installation is complete ...