Installation Manual
CA294-03070 rev 00
page 80 of 153
Install system components
1.
For each printing engine, unpack the section and perform the following:
a.
Install the PTE/air knife.
b.
Install the scorotron units.
c.
Install the cleaning station and wiper blade.
d.
Install the ITM cover.
e.
Thoroughly clean the BID units with imaging oil and a lint-free cloth.
f.
Install the BID units.
Make sure that the BID units are thoroughly clean before installing them. If necessary
re-clean the BID units.
g.
Install the Ametek filters.
Unpacking the ILP, unwinder, utility cabinets, and ink cabinets
1.
Unpack the ILP, unwinder, two utility cabinets and two ink cabinets.
2.
Lift and move the ILP, unwinder, utility cabinets, and ink cabinets to the raised floor platform.
If necessary, use a pallet jack to raise the units to the raised platform.