Installing a Smart Storage Battery
The server supports two Smart Storage Batteries, one each for the processor mezzanine board and the
system board.
Prerequisites
Before installing this option, be sure that you have the following:
• T-10 Torx screwdriver
• The components included with the hardware option kit
Procedure
1.
on page 38).
2.
Remove all power:
a.
Disconnect each power cord from the power source.
b.
Disconnect each power cord from the server.
3.
Do one of the following:
• Extend the server from the rack (
Extend the server from the rack
on page 38).
• Remove the server from the rack (
Removing the server from the rack
4.
on page 40).
5.
If installed, do the following:
a.
Remove the air baffle (
on page 42).
b.
Remove the processor mezzanine tray (
Removing the processor mezzanine tray
on page 47).
c.
Remove the 2P pass-through performance board (
Removing the 2P pass-through performance
on page 48).
6.
on page 46).
7.
Install the HPE Smart Storage Battery.
8.
Route and connect the cable.
Installing a Smart Storage Battery
103