Inspection Activities
Date Last Completed
Piping
1st Year 2nd Year 3rd Year 4th Year*
Near boiler piping
Check boiler and system piping for any sign of leakage; make sure pipes
are properly supported.
Vent
Check condition of all vent pipes and joints. Ensure the vent piping
terminations are free of obstructions and blockages.
System
1st Year 2nd Year 3rd Year 4th Year*
Visual
Do a full visual inspection of all system components.
Functional
Test all functions of the system (Heat, Safeties).
Temperatures
Verify safe settings on boiler or anti-scald valve.
Verify programmed temperature settings.
Glycol (If
Applicable)
Check glycol for the correct concentration, pH, and inhibitor level.
Electrical
1st Year 2nd Year 3rd Year 4th Year*
Connections
Check wire connections. Make sure connections are tight.
Smoke and CO
Detector
Verify devices are installed and working properly. Change batteries if
necessary.
Circuit Breakers
Check to see that the circuit breaker is clearly labeled. Exercise circuit
breaker.
Switch and Plug
Verify ON/OFF switch and convenience plug are both functional.
Chamber / Burner
1st Year 2nd Year 3rd Year 4th Year*
Combustion
Chamber
Check burner tube and combustion chamber coils. Clean according to
maintenance section of manual. Vacuum combustion chamber. Replace
any gaskets that show signs of damage.
Spark Electrode
Clean. Set gap as described in Figures 58 - 60. Clean probe with plumbers
cloth to remove oxides.
Combination
Ignitor and Flame
Probe
Check ionization in uA (d7 in Status Menu in Start-Up Procedures).
Record high fire and low fire. Clean probe with plumbers cloth to remove
oxides.
Condensate
1st Year 2nd Year 3rd Year 4th Year*
Neutralizer
Check condensate neutralizer. Replace if necessary.
Condensate Pipe
Disconnect condensate pipe. Clean out dirt. Fill with water to level of
outlet and reinstall. (NOTE: Verify the flow of condensate, making sure
that the hose is properly connected during final inspection.)
Gas
1st Year 2nd Year 3rd Year 4th Year*
Pressure
Measure incoming gas pressure.
Pressure Drop
Measure drop in pressure on light off (no more than 1” WC).
Check Gas Pipe for
Leaks
Check gas piping. Test for leaks and signs of aging. Make sure all pipes are
properly supported.
Combustion
1st Year 2nd Year 3rd Year 4th Year*
CO / CO2 Levels
Check CO and CO2 levels in exhaust. See Start-Up Procedures for ranges.
Record at high and low fire.
Safeties
1st Year 2nd Year 3rd Year 4th Year*
ECO (Energy Cut
Out)
Check continuity on flue and water ECO. Replace if corroded.
Sensors
Check wiring. Verify through ohms reading.
Final Inspection
1st Year 2nd Year 3rd Year 4th Year*
Check List
Verify that you have completed entire check list. WARNING: FAILURE TO
DO SO COULD RESULT IN SERIOUS INJURY OR DEATH.
Homeowner
Review what you have done with the homeowner.
Table 34 - *Continue annual maintenance beyond the 4th year as required.