UPS5000-E-(40 kVA-320 kVA)
User Manual
3 Installation
Issue 10 (2015-09-15)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
45
Figure 3-6
Raising the leveling feet
Step 9
Push the cabinet along the sliding plate to the floor.
----End
3.2 Installing a Single UPS
The top entry cabinet applies only to the UPS5000-E-320K-F320.
The input PDC, output PDC, top outlet kit, and IP21 component apply only to the
UPS5000-E-120K-F120 and UPS5000-E-200K-F200.
The other components are optional for the four models of UPS5000-Es.
3.2.1 Installing the Cabinet
Secured Installation
Step 1
Determine the position for installing the cabinet. Mark mounting holes based on the drawings,
as shown in