UPS5000-E-(40 kVA-320 kVA)
User Manual
3 Installation
Issue 10 (2015-09-15)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
47
Knock the expansion bolts into the holes until the expansion tube completely fits into the hole.
The expansion sleeves must be completely buried under the ground to facilitate subsequent
installation.
Figure 3-9
Installing expansion bolts (unit: mm)
1.
Drill holes in the ground by using a hammer drill. The hole depth is 52 mm to 60 mm.
2.
Partially tighten the expansion bolt and vertically insert it into the hole. Knock the
expansion bolt using a rubber mallet until the expansion sleeve is fully inserted into the
hole.
3.
Partially tighten the expansion bolt.
4.
Remove the bolt, spring washer, and flat washer.
Step 3
Slide the cabinet on its castors to the installation position.
Step 4
(Optional) If the castors of the UPS need to be lifted from the ground, perform steps
in
Step 5
Remove the rear panel of the cabinet, as shown in
, and then open the front door.