EDGE U0-6 Simplified Maintenance Manual
12 Replacing the P6's PCBA Without Removing the Battery
Issue 1.0 (2013-01-12)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
92
5. Install the protective racks for the TP/LCD BTB connector and motor
.
a. Install the motor protective rack, and fasten the three screws at a low speed with the torque of 0.8 kgf*cm.
You
can also manually fasten the screws.
Success criteria: No screws or threads are stripped out. b. Install the protective rack for the TP/LCD BTB
connector, and fasten the two screws at a low speed with the torque of 0.8 kgf*cm.
You can also manually fasten
the screws.
Success criteria: No screws or threads are stripped out.
Figure 1
Figure 2
Figures 3 shows the phone with the protective racks for the TP/LCD BTB connector and motor properly installed.
Figure 3
6.Attach the PCBA tamper-resistant label and IMEI label, and manually install the battery
cover.