Figure 4-1
Space requirements for installing an EG860 (unit: mm)
Requirements for Operating Environment
For details about operating environment requirements, see
.
4.2 Installation Preparations
This section describes how to unpack and check the goods onsite and prepare installation tools
before EG860 installation.
Prerequisites
Upon the device arrival, inspect the device and ensure that the device is intact.
Verify that:
1.
The quantity of devices is consistent with the packing list.
2.
The shipping containers are intact.
3.
The types and number of devices in the shipping containers are consistent with the packing
list.
4.
The devices are intact.
If short, wrong, excessive or damaged goods are found, maintain the goods while contacting the
supplier as soon as possible.
Precautions
l
Power on an EG860 within 24 hours after unpacking it. If you power off an EG860 for
maintenance, restore power to the EG860 within 24 hours.
EG860
User Guide
4 Installation
Issue 02 (2015-04-10)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
30