5 Installing the Cabinet on an Underground Base
5.3 Laying the Underground Base
•
The underground base is heavy. This process requires multiple-person collaboration. Protect the underground base from
damage. Any crack or exposure of glass fiber on the post or panel caused by tool collisions is not allowed.
•
The pre-buried cables (or pipes) must rise slightly above the ground.
•
After the cables (or pipes) are pre-buried, use sealing materials to seal the cables (or pipes) outlet to prevent water
•
intrusion.
Gently place the underground base on the
concrete in the foundation pit, and use a spirit
level to level the underground base.
Lay 75-mm-deep concrete (with the same
concrete ratio) evenly at the bottom of the
underground base. Use a spirit level to level the
underground base.
Pre-bury cables (pipes) at the cable hole position on the underground base with the help of the line-drawing template
for the cabinet (type II).
Line-drawing Template for Cabinet (Type II)
Cable hole
Cable (or pipe)
Cable (or pipe)
NOTICE
Summary of Contents for F01T500
Page 1: ...HUAWEI TECHNOLOGIES CO LTD F01T500 Quick Installation Guide Issue 07 Date 2017 05 03 ...
Page 19: ...With battery cabinet 4 Installing the Cabinet on a Concrete Pedestal 14 ...
Page 23: ...18 Unit mm 4 Installing the Cabinet on a Concrete Pedestal ...
Page 25: ...20 4 Installing the Cabinet on a Concrete Pedestal ...
Page 27: ...22 4 Installing the Cabinet on a Concrete Pedestal ...
Page 38: ...33 With power meter box ...
Page 40: ...35 With power meter box AC power cables AC power cables ...
Page 44: ...39 6 Routing Cables 6 3 Diagram of Cable Connections Between the RPS and MDF RPS Power Supply ...
Page 51: ...46 Route the input Cables of the AC RPR power supply 6 Routing Cables ...
Page 83: ...14 FAQs for Installation 78 ...
Page 84: ...15 FAQs for Installation 79 ...