10 Powering On the Device (AC Power Supply)
74
•
The cabinet must be powered on within seven days after installation.
•
To ensure the safety, before powering on the device, check whether condensation exists in the cabinet. Power on the
device only after you ensure that no condensation exists. For the detailed method of removing condensation, see the
corresponding label on the cabinet front door.
•
During the power-on, before and after turning on each circuit breaker for the first time, you must use a multimeter to
check the input and output voltages and ensure that the voltages are normal.
(AC ranges: 200 V AC to 240 V AC; DC range: –42 V DC to –58 V DC)
•
After installing the cabinet and powering on the device, ensure that the battery switch is in the ON state. If the device
needs to be powered off, you must first turn off the battery switch and then turn off the AC switch.
Green: on for 1s and off for 1s repeatedly
LED for fan tray
AC PDU
Summary of Contents for F01T500
Page 1: ...HUAWEI TECHNOLOGIES CO LTD F01T500 Quick Installation Guide Issue 07 Date 2017 05 03 ...
Page 19: ...With battery cabinet 4 Installing the Cabinet on a Concrete Pedestal 14 ...
Page 23: ...18 Unit mm 4 Installing the Cabinet on a Concrete Pedestal ...
Page 25: ...20 4 Installing the Cabinet on a Concrete Pedestal ...
Page 27: ...22 4 Installing the Cabinet on a Concrete Pedestal ...
Page 38: ...33 With power meter box ...
Page 40: ...35 With power meter box AC power cables AC power cables ...
Page 44: ...39 6 Routing Cables 6 3 Diagram of Cable Connections Between the RPS and MDF RPS Power Supply ...
Page 51: ...46 Route the input Cables of the AC RPR power supply 6 Routing Cables ...
Page 83: ...14 FAQs for Installation 78 ...
Page 84: ...15 FAQs for Installation 79 ...