Figure 8-27 Cable interconnection position
Step 7 Install the electromagnetic valve.
NO TE
Do not install the electromagnetic valve when installing the fire cylinder for the first time. Install
the electromagnetic valve when commissioning the fire extinguishing system.
1. Remove the protective cover at the electromagnetic valve installation position
on the container valve. Align the electromagnetic valve and the container
valve, and tighten the electromagnetic valve clockwise.
Figure 8-28 Removing the electromagnetic valve protective cover
----End