FusionModule1000B Air-Cooled IT Solution
Maintenance Guide
2 O&M Preparations
Issue 02 (2017-01-10)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
6
Technical Manual
Function
Obtaining Method
(Remarks)
conditioner.
NetCol5000-A 25 kW & 35
kW Air-Cooled In-row
Precision Air Conditioner
User Manual (600 mm Width)
Describes how to use and
maintain 25 kW & 35 kW
air-cooled precision air
conditioners.
UPS5000-E-(40 kVA-320
kVA) User Manual
Describes how to use and
maintain the UPS5000-E.
UPS5000-E-(20 kVA-160
kVA) User Manual (Low
Voltage)
Describes how to use and
maintain the UPS5000-E.
FusionModule1000B
V100R003C00 Outsourced
Component Document
Package
Describes how to use and
maintain outsourced
components.
Download this document
from
the link is unavailable,
contact the local GTAC or
TAC.
2.3 Container Entry Requirements
The following describes the requirements for working in the FusionModule1000.
Item
Requirement
Before entry
Obtain the entry permit.
NOTE
The detailed operations are performed based on the requirements specified by the
manager of the FusionModule1000.
Entry
preparations
Obtain ESD clothes and shoes.
Remove dust from tools and materials that need to be taken into the
data center, and make a record.
Do not bring in forbidden items, such as storage devices, cameras, or
portable hard disks into the FusionModule1000.
Working in the
data center
Only professional personnel are allowed to work in the data center
and only in the presence of designated personnel.
Obtain permission from designated personnel and take necessary
precautions and preventive measures before entering the
FusionModule1000 and performing any operation which may affect
the normal running of the FusionModule1000.
Do not perform any unauthorized operations.
After all work
is finished
Pack up the tools and surplus materials.
Clean up and organize the equipment room environment according to