FusionModule1000A40 IT Solution
Maintenance Guide (2016.05, AI Version)
5 Components Replacement
Issue 04 (2018-01-05)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
67
5
Components Replacement
5.1 Replacing Power Supply and Distribution System
Components
5.1.1 Replacing a PD510 electricity meter
Prerequisites
A PD510 electricity meter needs to be replaced.
A spare PD510 electricity meter of the same model is available and functional.
When replacing a PD510 electricity meter, switch off the upper-level circuit breaker of the
PD510 electricity meter to be replaced.
Impact on the System
Certain services in the FusionModule1000 are interrupted.
Preparations
Tools: Phillips screwdriver, protective gloves
Materials: spare PD510 electricity meter
Documents: documents delivered with the PD510 electricity meter, initial configuration table
for the PD510 electricity meter
Skill requirement: power distribution system engineer
Procedure
Step 1
Remove the cabinet panel.