FusionModule1000A40 IT Solution
Maintenance Guide (2016.05, AI Version)
5 Components Replacement
Issue 04 (2018-01-05)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
93
Figure 5-19
Installing a LAN switch
Step 6
Reconnect all cables.
Step 7
Connect the power plug of the LAN switch.
Step 8
Check that the new LAN switch is working properly.
If the PWR1, PWR2, and SYS indicators of the LAN switch are on after power-on, the LAN switch is
working properly.
----End
Follow-up Procedure
Dispose of the removed LAN switch that is confirmed faulty.
5.3.6 Replacing the ECC500 Collector
Prerequisites
An ECC500 collector needs to be replaced.
A spare ECC500 collector of the same model is available and functional.
Impact on the System
The monitoring of the corresponding area is interrupted.
Preparations
Tools: cable cutter, Phillips screwdriver, small-sized flat-head screwdriver, insulation tape,
marker
Materials: spare ECC500 collector