Stage
Precautions
Before hoisting
Ensure that the crane and steel ropes provide the required bearing
capacity.
Ensure that the steel ropes are securely connected.
During hoisting
Do not allow any unauthorized people to enter the hazardous areas
and never stand under the crane arm during hoisting.
Ensure that the crane is properly located and avoid long-distance
hoisting.
Keep the pre-fab. module stable and horizontal during hoisting, and
ensure that the diagonal gradient of the pre-fab. module is within 5
degrees.
Lift and land a pre-fab. module slowly to prevent shock to
equipment inside it.
Remove the steel ropes after ensuring that the pre-fab. module is
placed evenly on the concrete platforms.
Preparations
Tools: crane, socket wrench, torque wrench, Phillips screwdriver, jack, steel hoisting rope,
level, level gauge, hammer drill, angle rule, marker, ink fountain, long leather measuring tape,
claw hammer, vacuum cleaner
Materials: pre-fab. module to be hoisted, expansion bolt, angle steel bracket
Skill requirement: skilled technician, common technician, crane driver
Procedure
Step 1
Adjust the pre-fab. module in the required direction, connect the steel hoisting ropes, and
hoist the pre-fab. module onto the concrete platforms.
When hoisting a pre-fab. module, ensure that the four corner fittings of the pre-fab. module
are aligned with the marked mounting positions for corner fittings on the concrete platforms.