FusionModule1000A20 Prefabricated All-in-One Data
Center
Installation Guide
6 Installing Devices Inside the Pre-fab. Module
Issue 02 (2020-01-15)
Copyright © Huawei Technologies Co., Ltd.
66
Figure 6-33
Battery installation position
Step 2
Connect the battery cables to the reserved power cable terminals.
Figure 6-34
Connecting battery cables
Do not connect the red positive cable until power-on commissioning.
Ensure that battery cables for the extinguishant control panel are connected to correct
polarities.
----End
6.5.3 (Optional) Connecting a Cable to the ASD Power Box
Battery
Prerequisites
The position of the ASD power box has been specified.
Documents delivered with the ASD power box have been obtained.