FusionModule1000A20 Prefabricated All-in-One Data
Center
Installation Guide
7 Installing a Cable Outside a Pre-fab. Module
Issue 02 (2020-01-15)
Copyright © Huawei Technologies Co., Ltd.
70
7
Installing a Cable Outside a Pre-fab.
Module
7.1 Installing External Input Power Cables
Prerequisites
Pre-fab. modules and external cable trays have been installed.
Preparations
Tools: crimping tool, Phillips screwdriver, adjustable wrench, cable cutter, heat gun
Materials: cable tie, cable, terminal, heat shrink tube
Skill requirement: skilled technician
Procedure
Step 1
Open the door of the main input PDB.
Step 2
Route the external input power cables into the pre-fab. module through the feeder window, as
shown in