FusionModule1000A20 Prefabricated All-in-One Data
Center
Installation Guide
8 Removing Transport Protection Materials
Issue 02 (2020-01-15)
Copyright © Huawei Technologies Co., Ltd.
78
No.
Device
Protection Materials
1
Photoelectric smoke
detector
Red cover, securing tape
2
Heat detector (optional)
Red cover, securing tape
3
Horn strobe (optional)
Securing tape
4
Fire alarm bell (optional)
Securing tape
5
Emergency light
Securing tape
6
Temperature and humidity
(T/H) sensor
Securing tape
7
Camera
Securing tape
----End
8.2 Removing Transport Protection Materials for
Intelligent Heat Exchangers
Prerequisites
The pre-fab. modules have been installed.
Preparations
Transportation protection materials are installed for intelligent heat exchangers in the
FusionModule1000.
Tools: step ladder, Phillips screwdriver
Materials: none
Skill requirement: common technician
Procedure
Step 1
Remove the protective cover from the intelligent heat exchanger.