FusionModule1000A20 Prefabricated All-in-One Data
Center
Installation Guide
3 Installation Preparations
Issue 02 (2020-01-15)
Copyright © Huawei Technologies Co., Ltd.
11
Preventive measures should be applied before installation to avoid water seepage into pre-fab.
modules and equipment in the case of a sudden change in the weather.
3.2 Installation Personnel Requirements
Installation personnel must be trained and qualified by Huawei to master methods for
system installation, and must obtain work permits before they begin to install the
equipment.
Technical personnel from the customer must be trained by Huawei and master the
installation method.
The number of construction personnel depends on the project progress and installation
environment.
Construction personnel have read through the safety precautions and related product
documents before they begin working.
Common technician: familiar with the equipment installation process.
Skilled technician: familiar with the equipment installation process and having an electrician
certificate.
3.3 Checking the Installation Environment
Check the site requirements one by one, and start installation only after all requirements are
met. Huawei will not be liable for any consequences caused if the installation environment
does not meet the requirements.
Mark the security zone: Use red caution belts to delimit a security zone, clean up obstacles in that zone,
and place construction signs and warning signs in eye-catching positions.