FusionModule1000A20 Prefabricated All-in-One Data
Center
Installation Guide
6 Installing Devices Inside the Pre-fab. Module
Issue 02 (2020-01-15)
Copyright © Huawei Technologies Co., Ltd.
40
6
Installing Devices Inside the Pre-fab.
Module
6.1 Installing Cooling Devices
6.1.1 (Optional) Installing the Fresh Air Integrated Unit
Prerequisites
Four installation positions are reserved of the pre-fab. Module. You need to install three of
them in sequence based on the site requirements.
Procedure
Step 1
Open the front panel of the smart cooling product, remove the two M8 nuts from the
compressor base, remove the two compressor fasteners, and tighten the two M8 bolts again, as
shown in the following figure.
Figure 6-1
Removing the compressor fixing plates
Step 2
Take off the cable connection box cover, supply air vent cover, and return air vent cover from
the pre-fab. module.