Maintenance
Area
Maintenance
Item
Operation
Expected Result Troubleshootin
g
Capacity test
(recommended)
-
When the UPS is
backed up,
discharge a
battery to the
undervoltage
alarm threshold,
to refresh the
capacity of the
battery.
1. Locate the
cause when
an exception
is identified.
2. If the fault
persists,
contact
Huawei
technical
support.
Battery
connection
-
1. When battery
strings are
powered off,
check the
reliability of
each
connection
point from
positive
terminals to
negative
terminals.
Check that all
points are
connected
reliably.
2. Use a torque
wrench to
check the
tightening
torque for
each battery
screw. The
torque meets
the
requirements
of the battery
manufacturer.
After
checking that
the battery
screws meet
the
requirements,
mark the
screws for
later check.
1. Rectify any
abnormal
connection.
2. If the fault
persists,
contact
Huawei
technical
support.
FusionModule500 Smart Mini Data Center
User Manual
6 O&M
Issue 02 (2020-12-25)
Copyright © Huawei Technologies Co., Ltd.
253