No.
Component
Onsite Installation
Onsite Cable
Connection
(8)
Smoke detector
Not required
Not required
(9)
3.5 kW split-type
air conditioner
Required
Required
NO TE
If the VCN or IVS1800, server, and LAN switch are configured, determine their installation
positions based on the site requirements.
4.1.5 Personnel Requirements
Only trained and qualified personnel who fully understand basic safety
precautions are allowed to install and operate a modular data center.
CA UTION
Huawei will not be liable for any consequence caused by the violation of this
document.
The requirements are as follows:
●
Customers' installation personnel must be trained by Huawei and understand
how to install and operate a modular data center.
●
The number of installation personnel varies based on the project progress and
installation environment. Typically, two to three persons are required.
4.2 Hardware Installation
The angle of door opening by the gas spring is 110°. Ensure that the door opening
angle is less than 110°.
4.2.1 Cabinet Transportation and Unpacking
Context
●
Only trained personnel are allowed to move the cabinet. Remove the packed
cabinet from the pallet using a pallet truck and move the cabinet to the
installation position.
●
To prevent the cabinet from falling over, secure it to the pallet truck using
ropes before moving it.
●
To prevent shocks or falls, move the cabinet gently. After placing the cabinet
in the installation position, unpack it and take care to prevent scratches. Keep
the cabinet steady during unpacking.