No.
Item
2
The power cables or the PGND cables are not inversely connected or short-
circuited.
3
The power cables and PGND cables are bound separately from other cables.
4
Labels are attached to both ends of the power cables, PGND cables, optical fibers,
and Ethernet cables.
5
The power cables and PGND cables are intact.
6
The power cables and PGND cables have no weld nugget.
7
No breaking device such as a switch or fuse lies in the electric connection of the
grounding system.
8
The redundant part of PGND cable is stripped off.
9
The lugs at both ends of the power cable or PGND cable are securely soldered or
crimped.
10
The flat washers and spring washers are fixed securely and closely at all the wiring
terminals.
11
The work GND cable and PGND cable of the BTS share a group of grounding
conductors with the lightning and GND cables of the building.
lists the check items of the signal cable connection.
Table 4-6
Checklist for the signal cable connection
No.
Item
1
The connectors of the signal cables must securely connected.
2
The connectors of the signal cables are intact.
3
The signal cables are intact.
4
The cable ties are evenly spaced. The signal cables are bound neatly with cable
ties to proper tightness, and arranged at even intervals in the same direction.
5
The extra length of the cable ties is cut and removed. The cut surfaces of the indoor
cables are smooth and have no sharp edges.
6
The cable layout facilitates maintenance and expansion.
7
Correct and clear labels are attached to both ends of the signal cables.
8
The distance between the bundled fiber tails and the RHUB panel is less than 70
mm.
LampSite
Installation Guide
4 Installing an RHUB
Issue 02 (2014-05-27)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
41