Figure 3-2 Connection diagram for bottom pipe routing
(1) Copper gate valve
(2) Y-shaped strainer
3.1.3 Material Preparations
Materials are classified to Huawei-provided, self-purchased, and onsite prepared
materials, which are marked as mandatory, optional, and engineering purchasing
in this document.
●
Mandatory: materials that are provided by Huawei and can be found in the
delivered fittings.
●
Optional: materials that can be purchased from Huawei or any other vendor
(if you have ordered the materials from Huawei, you do not need to purchase
them elsewhere). For details about the specifications of such materials to be
purchased, see the following sections.
●
Engineering procurement: materials that are not configured by Huawei and
need to be purchased from another vendor.
3.1.3.1 Automatic Drainpipe
The drainpipe supports the rigid pipe connection.