Figure 6-34
Using a buckle to secure the AC power cable
2.
Open the buckle, as shown in step 2 in
3.
Lock the buckle towards the joint between the AC power cable and socket and secure the
AC power cable to the socket, as shown in step 3 in
.
NOTE
Before fully closing the buckle, slide the buckle to a proper position where the power cable can be
tightly secured.
4.
for other power cables.
Step 3
Route and bundle cables.
NOTE
For details on how to route and bundle serial cables or management network cables, see
and
13 Basic Cable Routing and Bundling Technology
.
----End
6.23 Powering On the N8500
This section explains how to power on the N8500 after it is installed and cabled.
Prerequisites
Before powering on the N8500, ensure that:
l
All components have been properly installed and cabled.
l
The switch of PDU or PDB has been switched to
Off
.
l
The power voltage conforms to device requirements.
OceanStor N8500 Clustered NAS Storage System
Installation Guide (for T Series V100R005)
6 N8500 Installation (with S5500T Storage System as the
Storage Unit)
Issue 02 (2015-09-22)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
148