Figure 14-10
Peeling off the sheath
30mm
Max 5mm
3.
Install a shielded iron cover on the cable shield, and then insert the shielded iron cover into
the sheath along the crack. Install the shielded iron cover correctly, as shown in
.
Figure 14-11
Installing the shielded metal cover
Step 2
Install the wires.
NOTICE
When peeling off the sheath of the cable, do not damage the cable shield or the insulated wires.
1.
Use the diagonal pliers to peel the cable shield, grounding wire, aluminum foil, and
polyester band off the first 20 mm of the cable, leaving only the insulated conductors.
2.
Arrange the four twisted pairs properly and insert them into the wire fastening slot, as show
in
. Maintain the original twist pitch of the twisted pairs.
OceanStor N8500 Clustered NAS Storage System
Installation Guide (for T Series V100R005)
14 Making Cables and Connectors
Issue 02 (2015-09-22)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
315