Figure 5-2
Screw hole locations
Procedure
Step 1
Install the left adjustable guide rail (with an L identifier).
NOTE
If there is no scale marked on the channels, mark the scale from the bottom 1 U position upwards. Be sure
to horizontally line up the front and rear of the adjustable guide rail.
1.
Align the underside of the adjustable guide rail with the desired U position on the front and
rear channels.
2.
Extend the adjustable guide rail until the front and rear positioning pins protrude through
the holes on the front and rear channels.
3.
Use M6 screws to secure the adjustable guide rail.
OceanStor N8500 Clustered NAS Storage System
Installation Guide (for T Series V100R005)
5 N8500 Installation (with the S2600T Storage System as the
Storage Unit)