Figure 4-5 Opening the valve
Step 10 Observe the end pressure gauge on the front of the cabinet and record the
position of the pressure gauge pointer. 8 hours later, observe the pressure gauge
again. The position should remain unchanged.
----End
4.2.2 Installing Cabinets
Securing Installation
NO TE
If the optional antiseismic kits are configured, install the cabinet and antiseismic kits by
following the relevant instructions.
Step 1 Determine the cabinet installation position. Draw mounting holes in the
installation position according to the drawing.
SmartLi 2.0
User Manual
4 Installation
Issue 09 (2022-01-30)
Copyright © Huawei Technologies Co., Ltd.
47