Follow-up Procedure
Check that the cables are connected correctly and securely, and then seal the cable holes with
firestop putty.
5.6 Installation Verification
To ensure that the SUN2000 runs normally, check the SUN2000 after installation.
Check the following items after the SUN2000 is installed:
1.
The SUN2000 is installed correctly and securely.
2.
All screws, especially the screws used for electrical connections, are tightened.
3.
Ground cables are connected correctly and securely, with no open circuit or short-circuit.
4.
AC output power cables are connected correctly and securely, with no open circuit or
short-circuit.
5.
DC input power cables are connected correctly and securely, with no open circuit or
short-circuit.
6.
The DC input voltage is not higher than 1000 V and meets the local voltage range
requirements.
7.
RS485 communications cables are connected correctly and securely, with no open circuit
or short-circuit.
8.
Idle DC input terminals are sealed.
9.
The idle USB port and waterproof cable connectors are blocked with waterproof plugs.
5.7 Closing the Maintenance Compartment Door
Procedure
Step 1
Install the AC terminal cover, as shown in
Figure 5-35
.