UPS2000-G-(1 kVA-3 kVA)
User Manual (2016, Russia)
3 Installing the UPS
Issue 02 (2016-07-28)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
15
Figure 3-13
Connecting cables to the 3KRTS UPS input
3.5 Installation Verification
gives the installation verification checklist.
Table 3-2
Installation verification checklist
No.
Item
Acceptance Criterion
1
Cable routing
Cable routing meets engineering requirements.
2
Cable connections
Power cables and battery cables are tightened to
specified torques using a torque wrench,
connected correctly, and free of damage.
3
Cable connections for
USB ports and network
ports
Cables to USB ports and network ports are
connected correctly and securely.
4
Cable labels
Labels are neatly attached to both ends of each
cable, and the information on the labels is
concise and understandable.
5
Ground cable connection
The ground cable is securely connected to the
equipment room ground bar. Measure the
resistance between the UPS ground cable and the
equipment room ground bar, which must be less
than 1 ohm.
6
Distances between cable
ties
Distances between cable ties are the same, and
no burr exists.
7
Operating environment
Clean the conductive air and other sundries.