Figure 1-42 Drilling a hole and installing an expansion sleeve
(1) M12 bolt
(2) Spring washer
(3) Flat washer
(4) Expansion sleeve
(5) Expansion nut
(6) Concrete floor
Step 3 Move the UPS to the installation position over its castors.
Step 4 Lower the four leveling feet at the bottom of the cabinet using a wrench until all
the four castors at the bottom hang in the air and the leveling feet bear the whole
cabinet weight.
Step 5 Secure the L-shaped brackets to the chassis and secure the chassis to the floor.
1. Secure the two L-shaped brackets to the front and rear of the chassis.
2. Adjust the chassis to ensure that the expansion bolts align with the four half
holes beneath.
3. Check the chassis levelness using a level. If the chassis is not leveled, adjust
the leveling feet.
4. Secure the two L-shaped brackets to the floor.
Figure 1-43 Installing L-shaped brackets
Step 6 Reinstall the ground cable between the lower front panel and the chassis, and
reinstall the lower front panel.
UPS5000-A-(30 kVA–120 kVA)
Quick Guide