Figure 1-51 Leveling feet
(1) Edge of cabinet line on the scale plate
Step 7 Secure the chassis to the rack.
Figure 1-52 Securing the chassis to the rack
Step 8 Reinstall the power units and flip all ready switches to (ready).
Step 9 Reinstall the ground cable between the lower front panel and the UPS chassis, and
reinstall the lower front panel.
Step 10 Reinstall the upper front panel.
Step 11 (Recommended) Install a lock for the maintenance bypass switch, as shown in
.
----End
UPS5000-A-(30 kVA–120 kVA)
Quick Guide
1 Installation