Figure 1-72 Cable connections for a dual-bus system (60 kVA/80 kVA/120 kVA)
(1) Mains input power
cables
(2) Bypass input power
cables
(3) Battery cables
(4) Output power
cables
----End
1.5 Verifying the Installation
CA UTION
Carefully check items 09 and 10 listed in the table. If the check results of these
two items do not meet the acceptance criteria, the UPS may be damaged.
Table 1-7 Check items and acceptance criteria
No.
Item
Acceptance Criteria
01
Consistency between the
system configuration and
the product delivery
The system configurations, including
models and the number of units, comply
with the contract.
02
Cable layout
Cables are routed properly and meet
engineering requirements.
UPS5000-A-(30 kVA–120 kVA)