Figure 1-39 Lowering the leveling feet
Step 2 Check the chassis levelness using a level. If the chassis is not leveled, adjust the
leveling feet.
Step 3 Reinstall the ground cable between the lower front panel and the chassis, and
reinstall the lower front panel.
Step 4 Reinstall the upper front panel.
Step 5 To prevent misoperations, you are advised to install a lock (diameter of the
effective lock cylinder: 5–10 mm) for the maintenance bypass switch.
Figure 1-40 Lock for the maintenance bypass switch
----End
Tower-mounted Installation (Secured Installation)
Step 1 Determine the position for installing the UPS and mark mounting holes.
UPS5000-A-(30 kVA–120 kVA)
Quick Guide
1 Installation