5. Cut off the cable ties bound between holes of copper bars No. 23, 24, 25, 26, and 30. Install
soft copper bars in the bypass cabinet and its adjacent power cabinet from inside out. Then,
install soft copper bars No. 52.
6. Reinstall the removed No. 10 protection panel on the bypass cabinet and the filler panel on
the power cabinet.
3
Connecting Cables
1. This document describes cable routing by removing the top cover when there are two mains
inputs.
2. In the case of single mains, you do not need to connect bypass input power cables and
remove short-circuit copper bars.
UPS Cable Connection Reference
• Prepare cables away from the cabinets to prevent scraps from falling inside. Cable scraps may
ignite and cause personal injury or device damage.
• After cables have been installed, clean the cabinets in a timely manner. Keep the cabinets and
surrounding environment clean and tidy.
• You need to prepare terminals onsite. The stripped length of the copper wire should be the
same as that of the part of the terminal that covers the conductor.
3.1