Verifying the Installation
1. Check that there is no foreign matter at the top and bottom of the cabinets, copper bars, switches,
and the rear of units.
Front view
Rear view
2. After verifying the installation, reinstall all
the covers.
3. (Remove the paper protective film from the
sealing putty.) After routing cables and
verifying cable connections, seal the gap
between cables and the cabinet using
sealing putty.
Dustproof cover
4. Do not remove the dustproof cover before
power-on to prevent dust inside the UPS.
Sealing putty
Sealing putty must be used
as a whole and the gap can
be sealed only from the top.
Paper
protective film
5
Powering On and Starting the UPS
1. Before powering on the UPS, ensure that the UPS has passed all check items in the
UPS5000
Commissioning and Acceptance Report
and Chapter 4.
2. Measure the voltage and frequency of the UPS upstream input switch. The line voltage range is
138
–485 V AC, and the frequency range is 40–70 Hz.