3.2.2 Installing Batteries
Before installing batteries, read through the battery safety precautions and install batteries
as instructed in the delivered battery installation guide.
Install the batteries from the lower layer to the upper layer to ensure the system is secure
and balanced.
Install a battery rack and batteries. For details, see the battery installation guide delivered
along with the batteries.
3.2.3 Installing Optional Components
3.2.3.1 Installing Antiseismic Kits
Procedure
Step 1
Determine the installation positions for the antiseismic kits based on the delivered
marking-off template, and mark mounting holes.
Figure 3-15
Antiseismic kit mounting hole positions
Step 2
Secure two antiseismic kits to the front and rear of the cabinet using twelve M5x16 screws
and four M12 screws.