UPS5000-E-(360 kVA-480 kVA)
User Manual (40 kVA Power Modules)
3 Installation
Issue 07 (2020-01-10)
Copyright © Huawei Technologies Co., Ltd.
62
Figure 3-20
Installing expansion bolts (unit: mm)
1.
Drill holes in the ground by using a hammer drill. The hole depth is 52 mm to 60 mm.
2.
Partially tighten the expansion bolt and vertically insert it into the hole. Knock the
expansion bolt using a rubber mallet until the expansion sleeve is fully inserted into the
hole.
3.
Partially tighten the expansion bolt.
4.
Remove the bolt, spring washer, and flat washer.
Step 3
Use a pallet truck to move the cabinet to the installation position.
Step 4
Use eight M12x60 expansion bolts to secure the cabinet to the expansion bolt holes on the
ground and tighten the expansion bolts, as shown in
Figure 3-21
Tightening expansion bolts