UPS5000-E-(360 kVA-480 kVA)
User Manual (40 kVA Power Modules)
3 Installation
Issue 07 (2020-01-10)
Copyright © Huawei Technologies Co., Ltd.
65
This installation scenario uses common bolts rather than expansion bolts.
Step 3
Use a pallet truck to move the cabinet to the installation position.
Step 4
Use eight M12x45 bolts to secure the cabinet to the mounting holes in the channel steel and
tighten the bolts.
Step 5
Install the front and rear anchor baffle plates and left and right anchor baffle plates, as shown
in
Step 6
(Recommended) Install a lock for the maintenance bypass switch to prevent misoperations, as
shown in
. The required lock core diameter is 5–10 mm.
----End
3.2.2 Installing Antiseismic Kits
Install antiseismic kits only when the cabinet is floor-mounted.
Step 1
Determine the positions for installing the antiseismic kits. Mark mounting holes based on the
drawings.
shows the hole dimensions.
Figure 3-25
Mounting holes (Unit of measurement: mm)