UPS5000-S-1200 kVA
User Manual
3 Installation
Issue 04 (2019-06-25)
Copyright © Huawei Technologies Co., Ltd.
51
3.2 Single UPS Installation
When you install the UPS and connect cables, do not step on the front door baffle plate and
the door support at the bottom of the cabinet to prevent paint flake-off and deformation.
Otherwise, the front door will not be properly closed.
3.2.1 Installing a Cabinet
3.2.1.1 Floor Installation
Prerequisites
Ensure that the installation floor is flat.
Context
During delivery, two power units are transported separately, and the bypass unit and
input/output unit are transported together.
Procedure
Step 1
Determine the cabinet installation positions on the floor based on holes in the marking-off
template for floor installation.
A: mounting holes on the channel steel
B: mounting holes on the floor