UPS5000-S-1600 kVA
User Manual
3 Installation
Issue 04 (2020-03-03)
Copyright © Huawei Technologies Co., Ltd.
96
No.
Item
Acceptance Criteria
and cables
concise and easy to understand.
05
Cable ties
Cable ties are secured evenly and no burr exists.
06
Cable and busbar
connections
The input busbar, output busbar, and battery cables are
securely connected. For those secured by screws, the
spring washers are flattened.
07
Grounding
The resistance between the UPS ground bar and the
equipment room ground bar is less than 0.1 ohm.
08
AC phase sequence
The mains input, bypass input, and output phase
sequences are correct.
09
Battery cable
connections
The battery strings are correctly connected to the UPS.
10
Foreign matter cleaning
inside the cabinet
The inside and outside of the cabinet, and other
operating components, are free from conductive dust.
1.
There is no foreign matter (such as copper wires and
screws) on the top of the cabinet.
2.
There is no foreign matter on the copper bar
terminals.
3.
There is no foreign matter around switch terminals.
4.
There is no foreign matter on the bottom plate of the
cabinet.
5.
There is no foreign matter on the rear module
subrack.
1.
In the scenarios where holes are drilled for routing cables or covers are removed for routing cables,
after routing cables and checking cable connections, use sealing putty to fill in the gap between the
cables and the cabinet.
2.
After verifying the installation, reinstall all the covers.
3.
Do not remove the dustproof cover before power-on to prevent dust inside the UPS.