UPS5000-S-1600 kVA
User Manual
3 Installation
Issue 04 (2020-03-03)
Copyright © Huawei Technologies Co., Ltd.
63
3.2.2 Installing Busbars
Prerequisites
Before handling a busbar, wear protective gloves to avoid getting injured by sharp edges.
Move a busbar with caution to avoid scratching cabinets.
Each busbar weighs about 50 kg. Be cautious to avoid injury when moving heavy objects.
Preparation: two scaling ladders that are more than one meter high
At least two persons are required to carry a busbar. At least two persons are required to hold
the busbar on the top of the cabinet.
When moving a busbar, hold both ends of the busbar component. It is recommended that
the soft copper bar face downward.
Do not move the busbar upward by holding the soft copper bar.
Procedure
Step 1
Remove the front panels and dustproof covers from the top of the cabinets, and remove the
connecting kits at both ends of the top of the power unit 1 unit and power unit 3.
Figure 3-14
Removing front panels and dustproof covers
Step 2
Install the U-shaped sealing plate component (numbered 01).