UPS5000-S-1600 kVA
User Manual
3 Installation
Issue 04 (2020-03-03)
Copyright © Huawei Technologies Co., Ltd.
76
Figure 3-39
Connecting the signal cables
Step 9
Connect the signal cables between the power unit and bypass unit.
Table 3-7
Port mapping table
Cabinet Where the Signal Port Is
Located
Bypass Unit Port
Power unit 1
Signal (PWU1)
Power unit 2
Signal (PWU2)
Power unit 3
Signal (PWU3)
Figure 3-40
Connecting the signal cables
----End
3.3 Installing Optional Components
3.3.1 Installing a Battery Grounding Failure Detector
Prerequisites
If the power units share battery strings, you need to install a battery grounding failure
detector only in power unit 1.