3.1.1.2 Installation Clearances
Figure 3-1
Cabinet dimensions (unit: mm)
Reserve the following clearances around the cabinet to facilitate operations and ventilation:
Reserve at least 800 mm from the front of the cabinet.
Reserve at least 500 mm from the top of the cabinet.
Reserve at least 500 mm from the rear of the cabinet for ventilation.
−
Reserve at least 200 mm from the rear of the cabinet if there are ventilation
clearances reserved at the top, left, and right of the cabinet.
−
Reserve at least 800 mm if you need to perform operations at the rear of the cabinet.
3.1.2 Tools and Instruments
Insulate installation tools to prevent electric shocks.
Prepare the following tools and meters indicated in Table 3-1 for installation.
Table 3-1
Tools and meters
Tools and Meters
Electric pallet truck
Manual pallet truck
Ladder
Rubber mallet