UPS5000-S-600 kVA
User Manual (Three-phase, Three-wire)
3 Installation
Issue 05 (2019-12-20)
Copyright © Huawei Technologies Co., Ltd.
67
transformer
contact card
(4) Transformer input power
cables
(5) Cable between the
battery grounding failure
detector and fuse
----End
3.2.3.7 Connecting the iBattery
Procedure
Step 1
Connect the COM_OUT port on the iBOX of the iBattery to the COM2 port on the
monitoring interface card.
Figure 3-20
COM2 port
----End
3.2.3.8 Installing the Top Air-flow Cabinet
Procedure
Step 1
Install the Top Air-flow Cabinet.
For the installation method, see
UPS5000-(200 kVA-800 kVA) Top Air-flow Cabinet User
Manual
.
Step 2
Install a transformer.