Figure 4-34 Cable connection for the eLight system
NO TE
Whether the PE cable to the power module needs to be connected depends on the actual power
port.
----End
4.2.6 Installing a Smart Cooling Product
4.2.6.1 Materials
(Optional) Refrigerant R410A
If the one-way length of the pipe connecting the indoor and outdoor units is less
than or equal to 30 m, no R410A refrigerant needs to be purchased. If the length
is greater than 30 m and less than or equal to 80 m, R410A refrigerant needs to
be purchased.
FusionModule800 Smart Small Data Center
User Manual
4 Installation Guide
Issue 01 (2021-02-05)
Copyright © Huawei Technologies Co., Ltd.
119