Figure 4-15 Hoisting a NetCol500-A020 outdoor unit
Figure 4-16 Hoisting a NetCol500-A021 outdoor unit
----End
4.2.2 (Optional) Removing Aisle Containments
Prerequisites
The cabinets have been transported to the destination place and unpacked.
Context
If the site elevator is too small to transport a cabinet, remove the aisle
containment from the cabinet. Reassemble them after transporting them to the
installation position. Then perform subsequent operations.