Step 4 After the airflow sound disappears, reinstall the needle valve bonnet.
----End
4.2.6.5 Connecting the Refrigerant Pipe
4.2.6.5.1 Laying Out Pipes Inside a Cabinet
The gas pipe and liquid pipe used inside cabinets have been delivered to the site
as a pipe assembly, as shown in
Figure 4-50 Pipe assembly
(1) Liquid pipe
(2) Gas pipe
(3) Sheet metal
NO TE
●
describes how to route pipes inside a cabinet for the scenario with double
smart cooling products with top pipe routing. If there is only one smart cooling product,
only one assembly of gas pipe and liquid pipe is included.
● Secure the entire pipe assembly to the cabinet interior onsite, route pipes from the top
or bottom based on site requirements.
Top Pipe Routing
NO TICE
● When routing pipes from the top, do not route the pipes over servers or other
devices to protect the servers or other devices from being affected by pipe
leaks.
● Secure pipe fasteners to the cabinet.
●
Laying out pipes inside the Converged Cabinet
shows the pipe layout.