Step 3 (Optional) If you want to use the NTP server for time synchronization, select NTP
server sync. Set NTP primary server IP, NTP backup server IP, Port number, and
Sync interval (min), and click Submit.
----End
5.3.5 Adding a Southbound Device
Procedure
Step 1 Choose System Settings > Device Management > Add Device.
Step 2 After you add a device, date, and time based on the site requirements or click
Auto Discover Device, the details about the device connected to the smart
module are displayed.
Figure 5-13 Adding a device
----End
5.3.6 Creating a Smart Module Plan View
Procedure
Step 1 Choose Home > Plan View, create a micro-module in Micro-Module View and
set the layout and device quantity based on the actual micro-module scenario.
Step 2 Drag the icons of registered devices and devices on the cabinet list to appropriate
positions in the layout to create a micro-module plan view.
----End
5.3.7 Adding a UPS2000G
Prerequisites
One end of the straight-through cable has been connected to the RS485 port on
the UPS2000G, and the other end has been connected to the COM4 port on the
ECC800-Pro.
FusionModule800 Smart Small Data Center
User Manual
5 Power-On Commissioning
Issue 01 (2021-02-05)
Copyright © Huawei Technologies Co., Ltd.
276