8 Commissioning Core Components
Issue 02 (2019-12-20)
Copyright © Huawei Technologies Co., Ltd.
114
Figure 8-38
Red button of the emergency light
(1) Red button of the emergency light
The red button is located at one side of the emergency light.
If the result expected for each step appears, the emergency light is working properly.
----End
8.5.2.3 (Optional) Commissioning the VESDA
Preparations
Tool: smoke pistol
Documents: documents delivered with the VESDA, fire extinguishing device layout diagram,
power supply and distribution system diagram
Skill requirement: fire engineer
For the diagrams, see the initial configuration parameter manual for the solution in use.
Procedure
Step 1
Switch on the input power circuit breaker for the VESDA power box for the protected area
and connect the VESDA battery based on the power supply and distribution system diagram.
Step 2
(Optional) Perform power-on commissioning by following instructions in documents
delivered with the VESDA.
The VESDA is commissioned before delivery. A VESDA that is newly installed or used as a replacement
must be commissioned as instructed by the delivered documents.
Step 3
Release smoke in the protected area using the smoke pistol. Verify that the VESDA alarm
indicator lights up, and that an alarm is generated in the management system.